vue vxe-gantt 甘特图 table 依赖线的使用,新增与删除任务依赖连接线

93 阅读3分钟

vue vxe-gantt 甘特图 table 依赖线的使用,新增与删除任务依赖连接线,删除连接线的用法,通过设置 links 定义连接线,from 对应源任务的行主键,tom 对应目标任务的行主键

gantt.vxeui.com/

extend_gantt_chart_gantt_dependency_manual

过调用 setTaskLinks、clearTaskLinks 方法来设置或清除连接线可以很简单的画连接线或清除连接线

<template>
  <div>
    <vxe-button status="primary" @click="addLink1">新增一条线7-6</vxe-button>
    <vxe-button status="primary" @click="addLink2">新增二条线2-9</vxe-button>
    <vxe-button status="error" @click="delLink1">删除一条线7</vxe-button>
    <vxe-button status="error" @click="delLink2">删除一条线2</vxe-button>
    <vxe-button status="success" @click="updateLink1">重新设置连接线1</vxe-button>
    <vxe-button status="success" @click="updateLink2">重新设置连接线2</vxe-button>
    <vxe-button status="error" @click="clearLink">清除全部连接线</vxe-button>

    <vxe-gantt ref="ganttRef" v-bind="ganttOptions"></vxe-gantt>
  </div>
</template>

<script setup>
import { ref, reactive } from 'vue'
import { VxeGanttDependencyType } from 'vxe-gantt'

const ganttRef = ref()

const ganttOptions = reactive({
  border: true,
  height: 600,
  rowConfig: {
    keyField: 'id' // 行主键
  },
  taskBarConfig: {
    showProgress: true, // 是否显示进度条
    showContent: true, // 是否在任务条显示内容
    moveable: true, // 是否允许拖拽任务移动日期
    resizable: true, // 是否允许拖拽任务调整日期
    barStyle: {
      round: true, // 圆角
      bgColor: '#fca60b', // 任务条的背景颜色
      completedBgColor: '#65c16f' // 已完成部分任务条的背景颜色
    }
  },
  taskViewConfig: {
    tableStyle: {
      width: 480 // 表格宽度
    }
  },
  columns: [
    { type: 'seq', width: 70 },
    { field: 'title', title: '任务名称' },
    { field: 'start', title: '开始时间', width: 100 },
    { field: 'end', title: '结束时间', width: 100 },
    { field: 'progress', title: '进度(%)', width: 80 }
  ],
  data: [
    { id: 10001, title: '任务1', start: '2024-03-01', end: '2024-03-04', progress: 3 },
    { id: 10002, title: '任务2', start: '2024-03-03', end: '2024-03-08', progress: 10 },
    { id: 10003, title: '任务3', start: '2024-03-03', end: '2024-03-11', progress: 90 },
    { id: 10004, title: '任务4', start: '2024-03-05', end: '2024-03-11', progress: 15 },
    { id: 10005, title: '任务5', start: '2024-03-08', end: '2024-03-15', progress: 100 },
    { id: 10006, title: '任务6', start: '2024-03-10', end: '2024-03-21', progress: 5 },
    { id: 10007, title: '任务7', start: '2024-03-15', end: '2024-03-24', progress: 70 },
    { id: 10008, title: '任务8', start: '2024-03-05', end: '2024-03-15', progress: 50 },
    { id: 10009, title: '任务9', start: '2024-03-19', end: '2024-03-20', progress: 5 },
    { id: 10010, title: '任务10', start: '2024-03-12', end: '2024-03-20', progress: 10 },
    { id: 10011, title: '任务11', start: '2024-03-01', end: '2024-03-08', progress: 90 },
    { id: 10012, title: '任务12', start: '2024-03-03', end: '2024-03-06', progress: 60 },
    { id: 10013, title: '任务13', start: '2024-03-02', end: '2024-03-05', progress: 50 },
    { id: 10014, title: '任务14', start: '2024-03-04', end: '2024-03-15', progress: 0 },
    { id: 10015, title: '任务15', start: '2024-03-01', end: '2024-03-05', progress: 30 }
  ]
})

const addLink1 = () => {
  const $gantt = ganttRef.value
  if ($gantt) {
    $gantt.addTaskLink({ from: 10007, to: 10006, type: VxeGanttDependencyType.StartToStart })
  }
}

const addLink2 = () => {
  const $gantt = ganttRef.value
  if ($gantt) {
    $gantt.addTaskLink([
      { from: 10002, to: 10009, type: VxeGanttDependencyType.StartToStart },
      { from: 10003, to: 10001, type: VxeGanttDependencyType.FinishToFinish }
    ])
  }
}

const delLink1 = () => {
  const $gantt = ganttRef.value
  if ($gantt) {
    $gantt.removeTaskLink(10007)
  }
}

const delLink2 = () => {
  const $gantt = ganttRef.value
  if ($gantt) {
    $gantt.removeTaskLink(10002)
  }
}

const updateLink1 = () => {
  const $gantt = ganttRef.value
  if ($gantt) {
    $gantt.setTaskLinks([
      { from: 10001, to: 10002, type: VxeGanttDependencyType.FinishToFinish },
      { from: 10004, to: 10005, type: VxeGanttDependencyType.StartToStart },
      { from: 10005, to: 10006, type: VxeGanttDependencyType.FinishToStart },
      { from: 10013, to: 10012, type: VxeGanttDependencyType.StartToFinish }
    ])
  }
}

const updateLink2 = () => {
  const $gantt = ganttRef.value
  if ($gantt) {
    $gantt.setTaskLinks([
      { from: 10001, to: 10003, type: VxeGanttDependencyType.StartToStart },
      { from: 10008, to: 10004, type: VxeGanttDependencyType.FinishToStart }
    ])
  }
}

const clearLink = () => {
  const $gantt = ganttRef.value
  if ($gantt) {
    $gantt.clearTaskLinks()
  }
}
</script>

gitee.com/x-extends/v…